PROJECT INFORMATION

Project I.D. 1011-01-03/04/09

Lake Delton - Madison Road
Reconstruction of USH 151 - IH 90/94/39 Interchange and
Reconstruction of High Crossing Boulevard
IH 90/94/39, Dane County

First Year Construction (2000 or 2001)

Reconstruction of High Crossing Boulevard from East Springs Drive to Crossroads Drive is proposed for the year 2000. However, due to current funding levels and the tight time frame of this project, it is proposed to move this project from the year 2000 to the year 2001. It is proposed to reconstruct High Crossing Boulevard as a four-lane divided urban roadway, with a five-foot wide bicycle lane on each side of the roadway, and a five-foot wide sidewalk on the south side. The existing bridge over the interstate is proposed to be removed and replaced with a new bridge. It is proposed to keep High Crossing Boulevard open to traffic during construction, except for temporary closures during lane shifts. It is proposed to construct the south portion of the new bridge and the southerly section of the roadway while maintaining traffic on the existing road and bridge. Traffic will then be shifted to the new construction, the existing bridge will be demolished, and the northerly portion of the new bridge and roadway will be constructed. A retaining wall is proposed to be constructed between the roadway and the Young America property. Electric transmission and distribution towers and poles will be relocated by MG&E. Real estate acquisitions (or dedications) necessary for reconstructing High Crossing Boulevard will be done by the city of Madison.

The two existing bridges that carry the interstate highway over the CP Rail System track will also be widened and redecked. Two lanes of traffic in each direction on the interstate will be maintained during this construction.

The box culvert which carries Starkweather Creek under the interstate will be lengthened to accommodate the widened embankment for the interstate highway.

Second Year Construction (2001 or 2002)

The remainder of the work for reconstructing the existing USH 151 -IH 90/94/39 interchange is proposed for the year 2001. However, due to current funding levels and the tight time frame of this project, it is proposed to move this project from the year 2001 to the year 2002. This work includes construction of dual lane collector-distributor (C-D) roadways for westbound and eastbound interstate traffic, including two new bridges where the C-D roadways cross over USH 151. The loop ramps in the north and south quadrants of the interchange will be enlarged in order to provide longer weaving and merging distances on USH 151 and the interstate. A detention basin for stormwater management is proposed to be constructed in the north quadrant loop ramp. The pavement for USH 151 will be replaced from East Springs Drive to the match with the pavement constructed as part of the American Parkway Interchange project. The vertical profile of USH 151 will be lowered under the interstate highway by approximately 1-1/2 feet, in order to meet current vertical clearance standards under the interstate to improve safety.

It is proposed to keep the interstate highway and USH 151 open to traffic during construction. Shoulder closures and temporary lane closures will be required. Ramp movements will be maintained to the greatest extent possible by the use of temporary ramps, temporary intersections and temporary traffic signals.

Real estate acquisitions necessary for constructing the collector-distributor roadways south of High Crossing Boulevard will be done by the City of Madison for WisDOT.

Half Diamond Interchange at High Crossing Boulevard

The High Crossing Boulevard Ramps to and from the interstate highway will also be constructed during the second year of construction, if the requested change to interstate access report and associated environmental assessment document are approved by the Federal Highway Administration.

If approved, these ramps will be constructed at the beginning of the second year of construction, prior to reconstructing the existing ramps in the USH 151 -IH 90/94/39 Interchange.

Schedule

The current schedule is based on year 2000 and 2001 construction. However, as noted previously, the schedule for each of the two years of construction is proposed to be moved to the years 2001 and 2002, respectively.

 
Right of Way Acquisition for                       	Currently Scheduled to
High Crossing Boulevard Project                         Begin March 1999

Environmental Document Complete (assume FONSI)          August 1999

Open Bids for High Crossing Boulevard Project           March 2000 (or 2001)

Begin Construction of High Crossing Boulevard Project   May 2000 (or 2001)

Construction of High Crossing Boulevard                 November 2000 (or 2001)
Project Substantially Complete

Right of Way Acquisition for Interchange/               Currently Scheduled to 
Interstate Project                                      Begin November 1999

Open Bids for Interchange/Interstate Project            November 2000 (or 2001)

Begin Construction of Interchange/Interstate Project    March 2001 (or 2002)

Construction of Interchange/                            December 2001 (or 2002)
Interstate Project Substantially Complete


WC